Project Phoenix
Project Phoenix involved the installation of more than 2.2 million pounds of sheet metal ductwork and multiple specialty HVAC systems within a 1,000,000-square-foot semiconductor manufacturing facility. The project was delivered under an aggressive, fast-track one-year schedule and required extensive preplanning and close coordination with multiple trades.
Through strong leadership, detailed scheduling, and a skilled workforce, the ductwork installation was executed efficiently and completed within the condensed timeframe, meeting the demanding schedule and performance requirements of a high-tech manufacturing environment.

Scope
HVAC Duct Work
Duration
Aggressive, one-year fast-track schedule
Key Responsibilities
Coordination among multiple trades
Precise planning to ensure project deadlines were met
Project Details
Facility size: 1,000,000 square feet
Schedule: 12-month fast-track
Ductwork installed: 2.2 million pounds
Contract amount: $68 million